A fourth campus fully scored, and what's holding Longhorn down.
The gap. Our public book of 25 data-center power campuses shows 50,293 MW announced and 4,254 MW binding — signed, executed, or at financial close. That's a 46.0 GW gap; 91.5% of announced capacity carries no obligation. As of 15 Sep 2026; the public book did not move this week.
The scores. The Stentorian Delivery Index scores each campus 1–5 on five pillars: Power, Equipment, Grid, Construction, Binding. A campus only gets a score when all five have cited evidence. Week over week (Terminal snapshots 9 Nov → 16 Nov 2026):
| Campus | SDI | Power | Equip. | Grid | Constr. | Binding | WoW |
|---|---|---|---|---|---|---|---|
| IREN Childress, TX | 4.70 | 5 | 5 | 3 | 5 | 5 | — |
| xAI Colossus, Memphis/Southaven | 4.40 | 5 | 5 | 1 | 5 | 5 | — |
| Longhorn, Abilene, TX | 3.60 | 5 | 3 | 1 | 5 | 3 | NEW (was 4 of 5 pillars) |
| Fermi Project Matador, Amarillo, TX | 3.05 | 3 | 5 | 3 | 2 | 1 | — |
What moved: Longhorn's Equipment pillar got cited evidence on 12 Nov, so it joins the fully scored set. Microsoft Fairwater (Mount Pleasant) entered the tracked universe, taking it from 22 to 23 campuses.
Slippage Spotlight: Longhorn. On paper, Abilene is a success story — a source dated 5 Apr 2026 says the first 200+ MW is operational, and the build is financed (JPMorgan debt plus Crusoe/Blue Owl equity, same source). So why 3.60 and not 4-plus?
Equipment. GE Vernova reported (24 Jul 2025) that 10 LM2500XPRESS aeroderivative turbines were ordered in December 2024 for the site. That's "ordered." We have nothing on file showing they're on site. In the field, the gap between a PO and a set unit is where schedules go to die: factory slots, transport permits, rigging crews, pad readiness, commissioning. Current market lead time for a new aero turbine order in our data is 36 months (tier 1, observed 27 Oct 2026) — not this campus's clock, but a reminder of what a reorder would cost.
Grid. Taylor County residents raised concerns over tax breaks at a commissioners meeting (KTXS, 11 Feb 2025). Our rule scores documented community pushback a 1, and it overrides the regional default.
Binding scores 3: financing is on file, but we have no sourced lease or financial-close evidence covering the full build.
Coverage. 4 of 23 campuses fully scored, covering ~26% of the sourced announced MW in the Terminal (2,248 of 8,668 MW; two of the four campuses have no sourced capacity yet). Biggest blank pillar: Equipment, scored on only 4 of 23. Blanks are not zeros. Our bar for publishing a weighted index as "the market" is at least 10 fully scored campuses covering at least 50% of announced MW. We're not there, so you get campuses, not a headline number.
Campus-level critical-path audits, equipment queues, and binding evidence require institutional Terminal access.